planned labour cost reverts to zero after duration change - WHY?

D
Dean Pearcy 👤 Member for 20 years 2 months

I have numerous activities that contain a labour resource, say GANG1, that don't have a resource rate as a price is meaningless in this case. It's 2 men and a van, going on maintenance activities. I then know the budget of the 3d activity of work they are doing, say £6000. so I put this figure into the planned labour cost. If i then change this activity duration to 2d, the planned cost will revert to zero. I want the planned cost to stay the same, as that is how much this task will cost. Why does it revert to zero? What auto calculation is going on that I need to stop?

Many thanks in advance.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

turn off calculate cost from units 

you wil have to change this in the resources directory add a column for Calculate costs frorm units.

 

Also under the details tab on the right where it says profile uncheck calcluate costs from units

 

Also at the activity level you want to run a global change 

where resource equals GANG1

then calculate costs from units equals no

 

 

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts