Free Float

Dear all,

 

I want to indicate Free Float in MSP, both in a column and in the Gnatt bar, is it possible.

 

Regards,

satish

R
Rafael Davila 👤 Member for 22 years 4 months

Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.

So old no longer Photobucket pictures aer available.

 

Photobucket

R
Rafael Davila 👤 Member for 22 years 4 months

Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.

S
Satish Kumar 👤 Member for 16 years 5 months

 

 

I want to display the end date as per Free Slack. How to get the date as per free slack. Further, how to move a task to a free slack finish date without using constraints?

Ex: activity A1 takes 10 days to complete; in sequence, activity A2 takes 100 days to complete. If I plan taking up these two activities in different sections of a Highway, say S1A1, S1A2, S2A1, S2A2. 

 

S1A1 completes after 10days and the resources can move to S2A1 on the 11th day. But S2A2 starts after 100days (completion duration for S1A2), so i want to start S2A1 10 days before S2A2. I dont want to use direct date constraint, Any method like ALAP (ALAP is using Total Float) in MSP for that.

Please help!

Regards

Satish

R
Rafael Davila 👤 Member for 22 years 4 months

Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.

G
Gary Whitehead 👤 Member for 17 years 3 months

Yup.

 

 

The column you want to insert is called "Free Slack" in MSP

 

You can create a bar with start as "start", and finish as "free slack"

Featured Partner

Top Posters

James Williams
75 posts
Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
Elyar Safarov
1 posts

Our Partners