I want to display the end date as per Free Slack. How to get the date as per free slack. Further, how to move a task to a free slack finish date without using constraints?
Ex: activity A1 takes 10 days to complete; in sequence, activity A2 takes 100 days to complete. If I plan taking up these two activities in different sections of a Highway, say S1A1, S1A2, S2A1, S2A2.
S1A1 completes after 10days and the resources can move to S2A1 on the 11th day. But S2A2 starts after 100days (completion duration for S1A2), so i want to start S2A1 10 days before S2A2. I dont want to use direct date constraint, Any method like ALAP (ALAP is using Total Float) in MSP for that.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.
So old no longer Photobucket pictures aer available.
Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.
I want to display the end date as per Free Slack. How to get the date as per free slack. Further, how to move a task to a free slack finish date without using constraints?
Ex: activity A1 takes 10 days to complete; in sequence, activity A2 takes 100 days to complete. If I plan taking up these two activities in different sections of a Highway, say S1A1, S1A2, S2A1, S2A2.
S1A1 completes after 10days and the resources can move to S2A1 on the 11th day. But S2A2 starts after 100days (completion duration for S1A2), so i want to start S2A1 10 days before S2A2. I dont want to use direct date constraint, Any method like ALAP (ALAP is using Total Float) in MSP for that.
Please help!
Regards
Satish
Deleted by Rafael Davila as to avoid annoying requests to revive this discussion as it is older tha 3 years.
Yup.
The column you want to insert is called "Free Slack" in MSP
You can create a bar with start as "start", and finish as "free slack"