Export both Baseline+Current in one XER file?

Member for

16 years 3 months

its alwasy a good practice to copy the original baseline schedule for this exact purpose becasue once you assign it to another schedule it gets hidden.

as Tony said restore the baseline open both projects together then export 

Member for

15 years

Member for

17 years 1 month

thanks Tony for your illustration

Member for

15 years

use refliction in P6 it will include current schedule along with more than one baseline.

 

 

Essam

Member for

12 years 8 months

In the maintain baselines click restore to unlink the baseline, open both and export XER, the other person just needs to assign the baseline to the main project. then later on for updates you´d only need to send the main project and import it as updating.