Export both Baseline+Current in one XER file?

J
Jenny Ingco 👤 Member for 14 years 5 months

Dear All P6 Experts,

I have my current schedule and I already assigned Basline to it. I try to export my current schedule as XER file and send it by e-mail but the person who import it to his computer he can't see my assigned baseline? Is there method I can send them in correct way at the same time in one XER file?

 

Thank you all,

 

Hanson 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

its alwasy a good practice to copy the original baseline schedule for this exact purpose becasue once you assign it to another schedule it gets hidden.

as Tony said restore the baseline open both projects together then export 

A
Alida Prinsloo 👤 Member for 15 years 7 months
E
Essam AbdulFattah 👤 Member for 15 years 7 months

use refliction in P6 it will include current schedule along with more than one baseline.

 

 

Essam

T
Tony Cabezon 👤 Member for 13 years 3 months

In the maintain baselines click restore to unlink the baseline, open both and export XER, the other person just needs to assign the baseline to the main project. then later on for updates you´d only need to send the main project and import it as updating.

Forum Sponsor

Top Posters

Nigel Hussey
1 posts
James Williams
74 posts
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts