Dear All P6 Experts,
I have my current schedule and I already assigned Basline to it. I try to export my current schedule as XER file and send it by e-mail but the person who import it to his computer he can't see my assigned baseline? Is there method I can send them in correct way at the same time in one XER file?
Thank you all,
Hanson
its alwasy a good practice to copy the original baseline schedule for this exact purpose becasue once you assign it to another schedule it gets hidden.
as Tony said restore the baseline open both projects together then export
P { margin-bottom: 0.21cm; }A:link { }
Good Day All,
I am currently working on Primavera 6 version 8.1. I there a option to export the project baseline and the current execution schedule altogether? If the there is now other way. I guess the only why is to release the project baseline and restore the baseline and to export both the exceution schedule and the baseline.
What are your thougths out there?
Kind Regards,
Alida
thanks Tony for your illustration
How to use refliction?
syed
use refliction in P6 it will include current schedule along with more than one baseline.
Essam
In the maintain baselines click restore to unlink the baseline, open both and export XER, the other person just needs to assign the baseline to the main project. then later on for updates you´d only need to send the main project and import it as updating.