When analysisng predecessors and successors I often roll up my programme so only a few WBS-levels are shown. I then open that WBS-level where the activity I want to analyse is located in.
When pushing either the "GoTo" for the predecessor or successor panels in the "Relationships"-tab at the bottom, I would like the WBS-level to open automatically and show the pred./succ.-activity, however that doesn't happen.
I can of course push "Expand All" under the View-tab and it will then automatically jump to the pred./succ.-activity, but then the whole programme will be shown again and I can start all over rolling up WBS-levels until I get what I want to see again. A lot of time wasted.
Is there any settings or short cuts to only open the WBS-level where the relevant pred./succ.-activity is located in.
Best regards,
Bo
no
Bo
I am fairly sure you will not get this from P6.
Regards
Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
http://www.eh.com.au, http://www.primavera.com.auand http://eastwoodharris.com.
Project Control Consultants and Planning and scheduling software book and training material publishers
Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/