PRIMAVERA Managing Percent Complete

Hi 

I have a project which I split into subprojects. 

Example 2 project are activity type projects and are just different disciplines but actually make up one project schedule. 

The 3rd project is a milestone schedule linked to the 2 activity schedules.

I would like to know if there is a way to make the milestone schedule have no weight on the performance % complete calulation for the 2 activity schedules?

 

if I open only the activty programs I get 20% complete, if i open all 3 I get 3% complete.

This does not make complete sense since the milestones don't even role up percent coplete into the wbs like the activity schedules do.

I understand it probably weighs down the progress simply because it adds weight to the schedules, being linked to them.

Is there a way for me to keep this structure, but remove the weighting of the milestones on the activity plans?

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Charlie

In the "Hint Help" you have a good explanation how the percent complete are calculated.

Under the tab Earned Value in the project and the wbs view check the settings for the percent complete calculation.

Maybe it will be better, after agreement of pm, to use a different percent complete type.

Dieter

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts