Hi
I have a project which I split into subprojects.
Example 2 project are activity type projects and are just different disciplines but actually make up one project schedule.
The 3rd project is a milestone schedule linked to the 2 activity schedules.
I would like to know if there is a way to make the milestone schedule have no weight on the performance % complete calulation for the 2 activity schedules?
if I open only the activty programs I get 20% complete, if i open all 3 I get 3% complete.
This does not make complete sense since the milestones don't even role up percent coplete into the wbs like the activity schedules do.
I understand it probably weighs down the progress simply because it adds weight to the schedules, being linked to them.
Is there a way for me to keep this structure, but remove the weighting of the milestones on the activity plans?
do not expect percent complete to roll up because you have have different percent completes for different activities. This is like asking to compaire apples and oranges. I have a more detailed explaination of percent complete at the link listed below.
http://pmsite.com/forums/viewthread/3029/
http://pmsite.com/forums/viewthread/3029/
Hi Charlie
In the "Hint Help" you have a good explanation how the percent complete are calculated.
Under the tab Earned Value in the project and the wbs view check the settings for the percent complete calculation.
Maybe it will be better, after agreement of pm, to use a different percent complete type.
Dieter