Early Remaining Units showing on Data Date...why ?

I
Irfan Khan 👤 Member for 16 years 11 months

hi to all experts,

 

i have a query to ask about the Remaining Early Units because right now i have prepared my recovery schedule & my Data Date is 12 Sep 2014, furthermore my 1st day of Week is Friday. 

The Problem that my Remaining Early Units shows on 12 Sep 2014 rather than showing by 19 Sep 2014 which is my next week plan as you can see in the attaached snapshot, eventhough i have checked my calenders, constraints & non of the activity have negative float.

any help in this regard will be highly appreciated

early_units.jpg

 

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if all of the predcessors to this activity have been complted then the earliest that this resouce can being is on the data date. Therfore what is shown is the correct under the usage spreadsheet option

S
Shah. HB 👤 Member for 17 years 6 months

Hi Irfan,

In CPM network, data date is the starting point for scheduling the activities and its associated units (Resources)

Therefore, your snapshot is correct and clearly shows there are scheduled activities planned to start on 12 Sep 2014.

 

Cheers

Shahul Badhusha

K
Kannan CP 👤 Member for 18 years

hi irfan,

data date of 12th sept means the progress up to 11th sept is recorded and the remaining units will start or distributed from 12th sept itself.

Regards

Kannan

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts