P6 - Budget at task level and Actuals at Summary level

Member for

18 years 9 months

Mel

WBS-summary is always related to a wbs. Relationships can be assigned but are ignored. I would use them because costs in general are related to a wbs.

LoE covers a group of activities independent from a wbs. You'll need a predecessor and a successor. 

Regards

Dieter

Member for

12 years

Is there any difference between using a LOE task to spread cost or a WBS summary task?

Member for

12 years

Is thre any difference between using a LOE task to spread cost or a WBS summary task?

Member for

18 years 9 months

Hi Mel

If you do a detailed planning in P6 it is quite common to do cost- and resource planning on a higher level. Try level of effort (similar to hammocks) type activities which span over a group of activities for the assignments.

Good planning!

Dieter