Oracle Primavera - PM6 Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Thu, 2014-08-28 20:11 Permalink Mel WBS-summary is always Mel WBS-summary is always related to a wbs. Relationships can be assigned but are ignored. I would use them because costs in general are related to a wbs. LoE covers a group of activities independent from a wbs. You'll need a predecessor and a successor. Regards Dieter Member for 12 years Member for 12 years Submitted by mcambrose on Thu, 2014-08-28 19:45 Permalink Is there any difference Is there any difference between using a LOE task to spread cost or a WBS summary task? Member for 12 years Member for 12 years Submitted by mcambrose on Thu, 2014-08-28 19:44 Permalink Is thre any difference Is thre any difference between using a LOE task to spread cost or a WBS summary task? Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Thu, 2014-08-28 17:51 Permalink Hi Mel If you do a detailed Hi Mel If you do a detailed planning in P6 it is quite common to do cost- and resource planning on a higher level. Try level of effort (similar to hammocks) type activities which span over a group of activities for the assignments. Good planning! Dieter Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Thu, 2014-08-28 20:11 Permalink Mel WBS-summary is always Mel WBS-summary is always related to a wbs. Relationships can be assigned but are ignored. I would use them because costs in general are related to a wbs. LoE covers a group of activities independent from a wbs. You'll need a predecessor and a successor. Regards Dieter
Member for 12 years Member for 12 years Submitted by mcambrose on Thu, 2014-08-28 19:45 Permalink Is there any difference Is there any difference between using a LOE task to spread cost or a WBS summary task?
Member for 12 years Member for 12 years Submitted by mcambrose on Thu, 2014-08-28 19:44 Permalink Is thre any difference Is thre any difference between using a LOE task to spread cost or a WBS summary task?
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Thu, 2014-08-28 17:51 Permalink Hi Mel If you do a detailed Hi Mel If you do a detailed planning in P6 it is quite common to do cost- and resource planning on a higher level. Try level of effort (similar to hammocks) type activities which span over a group of activities for the assignments. Good planning! Dieter
Member for
18 years 9 monthsMel WBS-summary is always
Mel
WBS-summary is always related to a wbs. Relationships can be assigned but are ignored. I would use them because costs in general are related to a wbs.
LoE covers a group of activities independent from a wbs. You'll need a predecessor and a successor.
Regards
Dieter
Member for
12 yearsIs there any difference
Is there any difference between using a LOE task to spread cost or a WBS summary task?
Member for
12 yearsIs thre any difference
Is thre any difference between using a LOE task to spread cost or a WBS summary task?
Member for
18 years 9 monthsHi Mel If you do a detailed
Hi Mel
If you do a detailed planning in P6 it is quite common to do cost- and resource planning on a higher level. Try level of effort (similar to hammocks) type activities which span over a group of activities for the assignments.
Good planning!
Dieter