P6 - Budget at task level and Actuals at Summary level

M
Mel Ambrose 👤 Member for 12 years 8 months

I would like to enter budget cost by loading resources and expenses on activities (for example carpenter 8 hrs, truck 1 day, lumber $250), but our accounting system tracks cost at a higher level, so I would like to enter actuals at a higher level. Is this doable? When I tried entering actuals at the summary level, I couldn't find a way to add summary cost without adding resources, and if I add resources then I am addinig to the man-hours in the schedule. I am new to using P6 for cost, so I may simply be exposing my ignorance. Any help is appreciated.

D
Dieter Wambach 👤 Member for 19 years 5 months

Mel

WBS-summary is always related to a wbs. Relationships can be assigned but are ignored. I would use them because costs in general are related to a wbs.

LoE covers a group of activities independent from a wbs. You'll need a predecessor and a successor. 

Regards

Dieter

M
Mel Ambrose 👤 Member for 12 years 8 months

Is thre any difference between using a LOE task to spread cost or a WBS summary task?

M
Mel Ambrose 👤 Member for 12 years 8 months

Is there any difference between using a LOE task to spread cost or a WBS summary task?

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Mel

If you do a detailed planning in P6 it is quite common to do cost- and resource planning on a higher level. Try level of effort (similar to hammocks) type activities which span over a group of activities for the assignments.

Good planning!

Dieter

Forum Sponsor

Top Posters

James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts