Primavera automaticaly inputting budegeted labour unit?

Z
Zoltan Palffy 👤 Member for 16 years 11 months

recourses can not automatically assign themselves to activities so someone had to do this 

S
Syam Mohan 👤 Member for 10 years 2 months

hello everyone,

                      I want to create generate histogram for office staff and direct labour. How it is possible.?

 

G
Godstime Mega 👤 Member for 11 years 11 months

hello everyone here , please i wanted to know more about  (REMAINING UNIT/TIME and AT COMPLETE UNIT) the reason i wanna know is that if  I assign 1 to my  REMAINING  UNIT/TIME , MY AT COMPLETE will automatically change to 42 , when its  remaining unit is 2 my at complete will automatically change to 84..... please  can anyone help on how to go about the calculations

thanks

R
Rodel Marasigan 👤 Member for 19 years 7 months

Sorry John,

The old Knowledgebase site is gone and redirecting to Oracle site. I logon and tried to find but nothing found.

There must be some patch like SP1 & SP2 but I’m not sure. What version of P6 are you using? I have 6.1 & 6.2 and both of them don’t have problem.

J
John Paul Augustine 👤 Member for 16 years 3 months

Yor are correct Mr. Rodel

But i find in internet that this type of error is occuring in P6 commonly.

I am pasting that link here

http://forums.oracle.com/forums/thread.jspa?messageID=3378954

in this link it is mentioned that

Please

reference Solution ID

prim18501 in

our Knowledgebase for anothere cause and more

information on "No resources assigned but Budgeted

Planned Labor units does not equal zero (0)"



but i couldn’t access to this knowledgedata base?

can you please check with this

R
Rodel Marasigan 👤 Member for 19 years 7 months

John,

If the Project was inherit or import from others you don’t have any control on what’s on the file until you manage to fix it. If the Project was newly created by you then you are aware of the history whether you did something or not.

J
John Paul Augustine 👤 Member for 16 years 3 months

Thank you Mr. Rodel..

but i find the same problem with other project plan also..

what may be possible reason for that?

J
John Paul Augustine 👤 Member for 16 years 3 months

No i didn’t input any cost in the Activity Detail-> Status tab-> Labor Cost -> Budget field..



I already corrected by filling down the budgetted labour units to zero manually..

But i should like to know why it is coming like this?

is there any settings i need to change in Primavera????/

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi John,

Did you put any cost on the Activity Detail-> Status tab-> Labor Cost -> Budget field?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts