recourses can not automatically assign themselves to activities so someone had to do this
hello everyone,
I want to create generate histogram for office staff and direct labour. How it is possible.?
hello everyone here , please i wanted to know more about (REMAINING UNIT/TIME and AT COMPLETE UNIT) the reason i wanna know is that if I assign 1 to my REMAINING UNIT/TIME , MY AT COMPLETE will automatically change to 42 , when its remaining unit is 2 my at complete will automatically change to 84..... please can anyone help on how to go about the calculations
thanks
Thank you Mr. Rodel for your reply...\
I am using Primavera 6.0...
Sorry John,
The old Knowledgebase site is gone and redirecting to Oracle site. I logon and tried to find but nothing found.
There must be some patch like SP1 & SP2 but Im not sure. What version of P6 are you using? I have 6.1 & 6.2 and both of them dont have problem.
Yor are correct Mr. Rodel
But i find in internet that this type of error is occuring in P6 commonly.
I am pasting that link here
http://forums.oracle.com/forums/thread.jspa?messageID=3378954
in this link it is mentioned that
Please
reference Solution ID
prim18501 in
our Knowledgebase for anothere cause and more
information on "No resources assigned but Budgeted
Planned Labor units does not equal zero (0)"
but i couldn’t access to this knowledgedata base?
can you please check with this
John,
If the Project was inherit or import from others you dont have any control on whats on the file until you manage to fix it. If the Project was newly created by you then you are aware of the history whether you did something or not.
Thank you Mr. Rodel..
but i find the same problem with other project plan also..
what may be possible reason for that?
John,
Thats the reason why. He might do something that you are not aware of.
I am not the one who create this program.
Actually i import it from other person...
John,
Did you create the Project or inherit/ import from someone?
No i didnt input any cost in the Activity Detail-> Status tab-> Labor Cost -> Budget field..
I already corrected by filling down the budgetted labour units to zero manually..
But i should like to know why it is coming like this?
is there any settings i need to change in Primavera????/
Hi John,
Did you put any cost on the Activity Detail-> Status tab-> Labor Cost -> Budget field?