Hello,
I am struggling to create a filter required by my owner between updates- below are the requirements:
"Activities within 14 calendar days of the critical path that were planned to occur during the updated period, but which did not occur or occurred later than the scheduled late start or late finish date, shall be identified and accompanied with an explanation for those delays."
Hi Chris,
First, you need to define your critical activities in >Scheduling Options and second, you can use range or multiple filters to achieved the output you want in P6. If you are referring to the baseline, you can use the baseline start and finish dates and range of 2 weeks from data date.
Regards,
Daniel
Hi Chris,
You'd need to do this in Excel. Try the following steps.
You will need to present your results in Excel.
=jerome
I don't think it's doable just with filters -I don't think the baseline late dates are a field you can filter on.
You could probably manage it by exporting your baseline to excel & re-importing BL late dates as user date fields (which are filterable)