Linking activities based on physical % complete

Hello evereyone,

Is there any method by which one can link an activity based on the predecessor's physical % complete in Primavera P6?

Linking SS or FS - is not serving the purpose.

Thanks in advance.

Haroon

H
Haroon Rasheed 👤 Member for 17 years 7 months

Hello Gary,

Thanks for the response.

Are you aware of any other software that can do it?

 

Haroon

G
Gary Whitehead 👤 Member for 17 years 2 months

Nope.

 

One of Primavera's major failings, this.

 

The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete.

 

Other alternative is to split the predecesor activity into 2, and use FS links

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts