Hello evereyone,
Is there any method by which one can link an activity based on the predecessor's physical % complete in Primavera P6?
Linking SS or FS - is not serving the purpose.
Thanks in advance.
Haroon
Hello evereyone,
Is there any method by which one can link an activity based on the predecessor's physical % complete in Primavera P6?
Linking SS or FS - is not serving the purpose.
Thanks in advance.
Haroon
Asta and Spider both have this facility.
Hello Gary,
Thanks for the response.
Are you aware of any other software that can do it?
Haroon
Nope.
One of Primavera's major failings, this.
The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete.
Other alternative is to split the predecesor activity into 2, and use FS links