BL Project Finish not matching BL Project Early Finish

M
Mark Sumner 👤 Member for 13 years 3 months

I am trying to show my baseline bars and it seems they are pulling from the BL Project Finish dates which are not correct and do not match the BL Project Early Finish Dates

1. How can I correct this so my BL Project Finish dates match the BL Project Early Finish dates(which are correct)?

2. is there a setting to have the bars reference the BL Project early finish dates and not the useless Project Finish Dates.

If by global change can you please post the setup as I can not seem to create the proper global change to make it work.

 

Thanks

Mark

M
Mike Testro 👤 Member for 20 years 5 months

Hi Mark.

It is the most likely result that the logic linked baseline programme will not equate to the contract completion date.

In fact if it does match exactly it is a sign that the programme has been rigged to suit.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts