I am trying to show my baseline bars and it seems they are pulling from the BL Project Finish dates which are not correct and do not match the BL Project Early Finish Dates
1. How can I correct this so my BL Project Finish dates match the BL Project Early Finish dates(which are correct)?
2. is there a setting to have the bars reference the BL Project early finish dates and not the useless Project Finish Dates.
If by global change can you please post the setup as I can not seem to create the proper global change to make it work.
Thanks
Mark
Mark,
Not entirely sure I understand your query, but I think if you read the following it will solve your issue:
http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf
Cheers,
G
Hi Mark.
It is the most likely result that the logic linked baseline programme will not equate to the contract completion date.
In fact if it does match exactly it is a sign that the programme has been rigged to suit.
Best regards
Mike Testro