BL Project Finish not matching BL Project Early Finish

M
Mark Sumner 👤 Member for 13 years 4 months

I am trying to show my baseline bars and it seems they are pulling from the BL Project Finish dates which are not correct and do not match the BL Project Early Finish Dates

1. How can I correct this so my BL Project Finish dates match the BL Project Early Finish dates(which are correct)?

2. is there a setting to have the bars reference the BL Project early finish dates and not the useless Project Finish Dates.

If by global change can you please post the setup as I can not seem to create the proper global change to make it work.

 

Thanks

Mark

M
Mike Testro 👤 Member for 20 years 6 months

Hi Mark.

It is the most likely result that the logic linked baseline programme will not equate to the contract completion date.

In fact if it does match exactly it is a sign that the programme has been rigged to suit.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts