Hours per TIME pERIOD

Dear Planners,

I have a project calendar, which is 6 days a week and 8 hrs/day, when I checked the hours per time period by clicking the button, I found hours/week is 40 not 48 and the hours/month, and hours/year as well have not been changed. So I have to change it manually. How it changes automatically once I change the hours per day?

Regards,

Moutaz

M
moutaz aldeib 👤 Member for 22 years 5 months

Dear Muhammad,

Thanks a lot for your reply, the project defauly calendar are already changed from the begining.

Regards,

Moutaz

M
muhammad anwar 👤 Member for 19 years 4 months

Dear Moutaz,

 

By changing projects default calendar the activity calendar does not change. If your activities are on 5 days calendar then they will stay on 5 day calendar but new activities you put in the project will pickup the new 6 day calendar. Diplay column for calendar and use fill down option to change the activities calendar and it will solve the issue.

 

Regards

Muhammad

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts