Dear Planners,
I have a project calendar, which is 6 days a week and 8 hrs/day, when I checked the hours per time period by clicking the button, I found hours/week is 40 not 48 and the hours/month, and hours/year as well have not been changed. So I have to change it manually. How it changes automatically once I change the hours per day?
Regards,
Moutaz
Dear Muhammad,
Thanks a lot for your reply, the project defauly calendar are already changed from the begining.
Regards,
Moutaz
Dear Moutaz,
By changing projects default calendar the activity calendar does not change. If your activities are on 5 days calendar then they will stay on 5 day calendar but new activities you put in the project will pickup the new 6 day calendar. Diplay column for calendar and use fill down option to change the activities calendar and it will solve the issue.
Regards
Muhammad