s-curve doesnt show reality

hi guys first of all sorry for my bad english i hope u understand.

in my schedule i have more than 2000 activities.i added wbs summary activity for each wbs.then i assigned budgeted (contrac price) and actual cost.some activities finished and some activities still on going.but i couldnt get s-curve how i want.s curve is here.whts the problem how can i solve this.please help

 

scurve.jpg

 

 

 

C
Chris Rymer 👤 Member for 16 years

Hi Ferhat

 

Have a look at Project Tracker, it creates S curves directly from P6 without the need to export the data to a spreadsheet. You can get a free trial and more product infromation at www.willmer.co.uk

M
Manochehr Hosseini 👤 Member for 23 years 4 months

What version of P6 are you using? I had similar problem when I was using P6 6.2, after I switched to version 7 it was solved.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts