dear all,
i encountered with the problem which seems something unrealistic : means u update my schedule & than i made a copy the current schedule as a my baseline.
here when i am looking @ my units its showing different for past month. whereas it should be the same asplanned.
please check the attachment for reference.
thanks…... [[wysiwyg_imageupload::]]

Hi,
Replace planned start with start and planned finish with finish.
Try the GC;
Then Planned start = start
And Next
If Planned finish is not equal to blank
Then Planned finish = finish
And Schedule the project.
Pl share if issue persist
- Ravi
Irfan,
I communicated this issue with oracle, no way to fix it with p6 for now, hopefully they consider it for future enhancement.
The only way that you have in your schedule is to divide in progress activities to 2 activity, and finished the first one on data date with a budgeted unit equal to actual, then you can assign the remaining unit to the second activity.
Regards,
Manochehr
Dear Irfan,
What option have you choosen there? If you choose "at completion value with current date" it should be Ok.
I tried that in many projects and it works.
If you like send the xer file to my email [email protected]. I will take a look.
Regards,
Manochehr
Dear, Manochehr Hosseini
i did the same & dates are matching but as far as planned & actual units are concerned its still showing difrent.
how to get this descrepencies pleaase let me know.
thanks....
thanks to reply....
i did this setting earlier & my planeed & actual date are ok. but the only budgeted unit are showing diffrent.
any clue ?.......thanks.....
Dear Irfan,
The simple solution for your problem is that you need to chnage the default setting of EV calculation as follow:
admin menu -----> admin prefrences---------> Earned value tab-----------> Earned value calculation tab-----------> change the settings to one of this option : "At Completion Values with current Dates" or "Budgeted Values With Current Dates"
Regards,
Manochehr
This is probably the common problem around planned dates
Check out Paul Harris' explanation of the issue, and how to correct:
http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf
Cheers,
G