Negative lag is the same as a ‘lead’ and advances the scheduled start (or finish) of the successor. Most authorities do not like ‘leads’ (eg, the DCMA 14 point check list: http://www.mosaicprojects.com.au/WhitePapers/WP1088_DCMA-14-Point.pdf ) However, particularly in high-level schedules and early in the schedule development cycle making the logical statement that ‘painting’ can start 2 weeks before the finish of ‘welding’ is reasonable if both activities are several months. As the level of detail builds in the schedule real links can replace the ‘lead’.
Positive lags delay the successor activity and are generally accepted as useful provided the lag does not replace an activity. Lags can be used to represent administrative lead times, to manage work flows or to represent mandated drying, curing, setting times when nothing can happen.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Can i know the Weight of connection bolts required to erect the pipe racks and othe steel structures ?
Hi everyone,
I would like to ask if what is the activity type of "SHOP DRAWING" when you make it as an activity, is this "Level of Effort" or "Task Dependent"...
Thanks
Negative lag is the same as a ‘lead’ and advances the scheduled start (or finish) of the successor. Most authorities do not like ‘leads’ (eg, the DCMA 14 point check list: http://www.mosaicprojects.com.au/WhitePapers/WP1088_DCMA-14-Point.pdf ) However, particularly in high-level schedules and early in the schedule development cycle making the logical statement that ‘painting’ can start 2 weeks before the finish of ‘welding’ is reasonable if both activities are several months. As the level of detail builds in the schedule real links can replace the ‘lead’.
Positive lags delay the successor activity and are generally accepted as useful provided the lag does not replace an activity. Lags can be used to represent administrative lead times, to manage work flows or to represent mandated drying, curing, setting times when nothing can happen.
Both need to be used with care and you need to understand how they are applied by your software (there’s no consistency). For ore on this see: http://www.mosaicprojects.com.au/PDF/Links_Lags_Ladders.pdf