Activity Finish Moving Ahead 1day

Hello,

There is a problem when i update the schedule and mark the activity as started my activity finish date automatically moves ahead. Example For an activity A my start date is 12.Oct.2013 and finish date is 15.oct.2013. When i update the schedule and move my data date to 13.Oct.2013 my finish date automatically moves to 16.Oct.2013 

R
Raymund de Laza 👤 Member for 16 years 6 months

Edit... User Preferences..... Dates.... Under the Time Click the button beside the Format you wish to display Time on the Dates Columns.

R
Raymund de Laza 👤 Member for 16 years 6 months

The issue is related with Time of the day... When ever updating any activity, consider the time start and time finish of activity.

R
Rafael Davila 👤 Member for 22 years 3 months

For started activities if you do no change remaining duration the finish date will usually be delayed after re-scheduling run to be DD+remaining duration unless any other reason such as out-of-sequence rules takes over and delays it even further. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts