Hello,
There is a problem when i update the schedule and mark the activity as started my activity finish date automatically moves ahead. Example For an activity A my start date is 12.Oct.2013 and finish date is 15.oct.2013. When i update the schedule and move my data date to 13.Oct.2013 my finish date automatically moves to 16.Oct.2013
Edit... User Preferences..... Dates.... Under the Time Click the button beside the Format you wish to display Time on the Dates Columns.
Raymund de Laza from where i can manage the time of an activity?
The issue is related with Time of the day... When ever updating any activity, consider the time start and time finish of activity.
For started activities if you do no change remaining duration the finish date will usually be delayed after re-scheduling run to be DD+remaining duration unless any other reason such as out-of-sequence rules takes over and delays it even further.