Time Sheet in p6

A
Amro Ahmed 👤 Member for 17 years 5 months

Dear All,

Please  anyone  could  inform me  how to update project  schedule through  time sheet in p6 specially, how prepare and  put the project time sheet  in p6 database to start update ?

A
Amro Ahmed 👤 Member for 17 years 5 months

How the primary resource  reflect  time sheet  is this in primavera file  and if in excel  or any other format how to prepare to match with primavera  to arrive for admin (P.M) to approve

I
Imran Arshad 👤 Member for 18 years 7 months

Hi Amro,

First you have assisgn activites to a primary resource and then that resource will be able to see his assigment in time sheet module. once allocated, resource can log actual units in time sheet module and will submitt you for approval. You will have notifcation for approval. After your approval these actual units will incorporate in Master Plan.

Brgds, Imran

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts