I use P3 to create the real cash Flow for the project most of the time and I dont have such problem. Could you please let me know in more detail whats your problem? You can use Excel to just make more fancy and colorful cash flow, but still the data should be calculated in P3.
Thanks very much, Jaco and Shahzad. But, I am very new to Exporting to Excel. I followed all the steps to P3 Look, where it sait Lotus file generated into p3.wk1 and got stuck. What do I do next to get my Excel Cash Flow Histogram ? Any help ? Expecting your valuable inputs!
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Much thanks Ali and Jaco. I really appreciate your helpful comments.
John,
I use P3 to create the real cash Flow for the project most of the time and I dont have such problem. Could you please let me know in more detail whats your problem? You can use Excel to just make more fancy and colorful cash flow, but still the data should be calculated in P3.
You can reach me at [email protected]
Cheers,
Ali Vessali
OK.
Easy you find the file called P3.wk1 and open it with xls.
How to find the file.
Well Open Windows Explorer.
And do a search.
After you have open the Data in xls just save it as something else in xls format.
Thanks very much, Jaco and Shahzad. But, I am very new to Exporting to Excel. I followed all the steps to P3 Look, where it sait Lotus file generated into p3.wk1 and got stuck. What do I do next to get my Excel Cash Flow Histogram ? Any help ? Expecting your valuable inputs!
John
Yes, Cash Flow Histrogram is more compatible and adjustable in Excel and that is the reason the planners prefer this in Excel.
Hi John
I can help with the part 1
Go -Tools-Graphic Report - Resource and Cost . Select RC 3 (Any one will Do)
Select Modify
Select the Criteria etc. Remember to change the dates.
On the Content Page a Thing called Display Data Values.
Pres Run and then you should have it.
I prefer exporting the Data to xls to the cahs flow.
Cheers