Ducting Installation rate

Hi Everyone,

This is my first post as I am a new entrant to planning. I am currently trying to estimate the productivity rates for ductwork and under in the M&E section, ducting is 1.2 to 1.5 sqm/day/man. 

I am confused with the use of square meter. So ductwork of 800x600mm for a run of 10 meters would take, Ductwork Square meterage [(0.8+0.6)*2]*10=28, then 28/1.2= 24 days for single person crew??

Some of team member go by measuring volume; which is correct?

Also, there is a pump , one active on standby, each pair for a wet riser and the other for sprinkler. We have no idea but we put 15 days for installation? Am I close?

 

Thanks in advance!

M
Mike Testro 👤 Member for 20 years 5 months

Hi Steven

It is best not to put too much faith in the PP rates section as they are not vetted by anybody.

Best to use an estimating handbook such as Spons M&E Services which follows the latest method of measurement..

Here the ductwork is classified as The Sum of Two Sides in mm so a 300 x 200 duct (or 400 x 100) would be 500 mm and the labour constant is set as 1.32 m per hour.

Dont forget the inline fittings - a fire damper is 18.48 hours each.

An 80 mm direct drive pump is 15 hours

A 150 mm pump is 38.5 hours.

Don't just guess - do some research.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts