Predecessor and Successor

Y
yifei 87 👤 Member for 13 years 3 months

Dear Sirs,

For P6, say Task A is the predecessor as Task B and Task C is the successor for Task B.

If I delete Task B, can the linking from Task A-Task B become Task A to Task C?

Thank you

Y
yifei 87 👤 Member for 13 years 3 months

Thank you very much.  I think this had solve my problems.

Have a nice day.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Gary

Alternatively you could change task B into a milestone to leave a record of the change.

Best regards

Mike Testro

G
Gary Whitehead 👤 Member for 17 years 2 months

Yifei,

 

If you delete Task B, you will have to manually add the link from Task A to Task C

If you instead dissolve Task B, Primavera will automatically add the new link for you

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts