For P6, say Task A is the predecessor as Task B and Task C is the successor for Task B.
If I delete Task B, can the linking from Task A-Task B become Task A to Task C?
Thank you
Dear Sirs,
For P6, say Task A is the predecessor as Task B and Task C is the successor for Task B.
If I delete Task B, can the linking from Task A-Task B become Task A to Task C?
Thank you
Thank you very much. I think this had solve my problems.
Have a nice day.
Hi Gary
Alternatively you could change task B into a milestone to leave a record of the change.
Best regards
Mike Testro
Yifei,
If you delete Task B, you will have to manually add the link from Task A to Task C
If you instead dissolve Task B, Primavera will automatically add the new link for you