P6 - Estimate To Complete

Hello

I am trying to use the Estimate to complete (ETC) as my Labor Units for my resource loading histograms.  However, when I go into my reports I am unable to create a report using ETC (only allows me to pick Remaining Units). 

 

Any suggestions?

K

K
Katie Coombs 👤 Member for 12 years 11 months

Benjamin,

I am trying to use unapproved PCN's & Productivity for the calculating my hours for my histograms.  However, I do not want to show this in my to Earn Budget (Will only Earn approved Scope). 

What i was hoping on doing is the following - creating a baseline showing my unapproved budgets + approved Budgets (BAC), however my project Budgeted manhours would only include the approved budgets.

Remaining would be Budget manhours - Actual units

Whereas ETC = PF*(BAC-Earned Value)

PF

Earned Values = BAC*Phy%

 

So I would want to show ETC values in my histogram instead of remaining Units.

K

F
Feng Benjamin 👤 Member for 15 years 4 months

Dear Katie,

 
Correct me if I am wrong, but ETC is the estimated labor to complete the activity and is computed as either the remaining total labor for the activity (Remanining Total Labor), or as PF * (Budget at Completion - Earned Value Labor). Hence, the remaining units that is found in the report should correspond to that.
 
Warmest Regards,
Benjamin

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts