Hello
I am trying to use the Estimate to complete (ETC) as my Labor Units for my resource loading histograms. However, when I go into my reports I am unable to create a report using ETC (only allows me to pick Remaining Units).
Any suggestions?
K
Hello
I am trying to use the Estimate to complete (ETC) as my Labor Units for my resource loading histograms. However, when I go into my reports I am unable to create a report using ETC (only allows me to pick Remaining Units).
Any suggestions?
K
Benjamin,
I am trying to use unapproved PCN's & Productivity for the calculating my hours for my histograms. However, I do not want to show this in my to Earn Budget (Will only Earn approved Scope).
What i was hoping on doing is the following - creating a baseline showing my unapproved budgets + approved Budgets (BAC), however my project Budgeted manhours would only include the approved budgets.
Remaining would be Budget manhours - Actual units
Whereas ETC = PF*(BAC-Earned Value)
PF
Earned Values = BAC*Phy%
So I would want to show ETC values in my histogram instead of remaining Units.
K
Dear Katie,