I tried it and it works.Lets say you have a planned value of 37000000, you devide it by 370000 and include % sign in the unit of measure.The planned value will be shown as 100% and actuals and earned value will be calculated and shown accordingly.Try it.
The meaning is to see the % of the total budget (total budget is 100%). to do this you have to divide through the total budget. Not a number like 10/100 or 1000.
Under activity profile/resource profile, choose profile options >graph tab > tick calculate average >devide the total shown on the profile by 10 if it is in 1000 and 100 if it is in 10000 and so on >type % in the units of measure> apply.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
hi guys
Thanks for the help. but can I keep different scales for the histogram and the curve and can i show the values (Data labels) as we can in excel.
sach
Dinesh,
Yes you’re right i misunderstood
You have to divide by your total budget and multiply by hundred (or as you say divide by total budget/100) works very fine.
Thanks
regards
Henk
Hi Henk,
I tried it and it works.Lets say you have a planned value of 37000000, you devide it by 370000 and include % sign in the unit of measure.The planned value will be shown as 100% and actuals and earned value will be calculated and shown accordingly.Try it.
Thanks & regards
Dinesh
Hi Dinesh,
I dont think this is the same.
The meaning is to see the % of the total budget (total budget is 100%). to do this you have to divide through the total budget. Not a number like 10/100 or 1000.
Regards
Henk
Hi,
May be you can try to use the following :
Under activity profile/resource profile, choose profile options >graph tab > tick calculate average >devide the total shown on the profile by 10 if it is in 1000 and 100 if it is in 10000 and so on >type % in the units of measure> apply.
Thanks & regards
Dinesh
Hi,
Its not possible to set % on one of the Axis.
You better make a timedistributed report, dump it to excel.
The new release will have this option (so im told).
Regards
Henk