Progress Curve

S
sachin sangai 👤 Member for 20 years 8 months

hi guys

Thanks for the help. but can I keep different scales for the histogram and the curve and can i show the values (Data labels) as we can in excel.



sach

H
Henk van der Heide 👤 Member for 21 years 10 months

Dinesh,



Yes you’re right i misunderstood

You have to divide by your total budget and multiply by hundred (or as you say divide by total budget/100) works very fine.



Thanks



regards



Henk

D
Dinesh Kumar Damavarapu 👤 Member for 24 years 3 months

Hi Henk,



I tried it and it works.Let’s say you have a planned value of 37000000, you devide it by 370000 and include % sign in the unit of measure.The planned value will be shown as 100% and actuals and earned value will be calculated and shown accordingly.Try it.



Thanks & regards



Dinesh

H
Henk van der Heide 👤 Member for 21 years 10 months

Hi Dinesh,



I dont think this is the same.

The meaning is to see the % of the total budget (total budget is 100%). to do this you have to divide through the total budget. Not a number like 10/100 or 1000.



Regards



Henk


D
Dinesh Kumar Damavarapu 👤 Member for 24 years 3 months

Hi,



May be you can try to use the following :



Under activity profile/resource profile, choose profile options >graph tab > tick calculate average >devide the total shown on the profile by 10 if it is in 1000 and 100 if it is in 10000 and so on >type % in the units of measure> apply.



Thanks & regards



Dinesh

H
Henk van der Heide 👤 Member for 21 years 10 months

Hi,



It’s not possible to set % on one of the Axis.



You better make a timedistributed report, dump it to excel.

The new release will have this option (so i’m told).



Regards



Henk

Forum Sponsor

Top Posters

Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts