Project resumption after long time of stoppage

Dear all

Whats the best way to make project resumption after stoppage for a long time ?

is to add stoppage period as nowork in calender or to make suspend and resume or to add new activites 

is there any advice ??

M
Mike Testro 👤 Member for 20 years 6 months

Hi Sabry

In that case use the calendar.

Best regards

Mike Testro

M
Mike Testro 👤 Member for 20 years 6 months

Hi Sabry

Another way is to set a progress data date at the time of restart with the same progress on tasks when stopped or 0% progress for work yet to start.

The calendar method would also work OK.

Best regards

Mike Testro