Dear all
Whats the best way to make project resumption after stoppage for a long time ?
is to add stoppage period as nowork in calender or to make suspend and resume or to add new activites
is there any advice ??
Dear all
Whats the best way to make project resumption after stoppage for a long time ?
is to add stoppage period as nowork in calender or to make suspend and resume or to add new activites
is there any advice ??
many thanks
Hi Sabry
In that case use the calendar.
Best regards
Mike Testro
yes i know but i want show that in that period work was stoped
Hi Sabry
Another way is to set a progress data date at the time of restart with the same progress on tasks when stopped or 0% progress for work yet to start.
The calendar method would also work OK.
Best regards
Mike Testro