Primavera P6 - Version 8.1 - Calendar Assignment Issue

Good Day All,

In Primavera P6 Version 8.1 I have developed a construction calendar that uses 10 hours work shifts. When I allocate this calendar to an activity with original duration of 5 days it changes the finish date of this activity to show completion of this activity on 4th day and not the 5th day as should be the case. Does anyone know the reason why Primavera computes the finish date that is ending at the end of 4th day but not the 5th? I am in a rush to complete my baseline so any help in solving this riddle is highly appreciated. My email address is: [email protected].

Thanks in advance for your time and efforts.

Mahavir Bhatt

M
Mahavir Bhatt 👤 Member for 13 years 4 months

Thank you Abilash, & Raymund,

I have found the answer to this puzzle. The trick lies in customizing the Time Period to match with the Hours / Work Shift. Thanks again for your help. Regards, Mahavir

M
Mahavir Bhatt 👤 Member for 13 years 4 months

Thank you Abilash, & Raymund,

I have found the answer to this puzzle. The trick lies in customizing the Time Period to match with the Hours / Work Shift. Thanks again for your help. Regards, Mahavir

Featured Partner

Top Posters

xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts
Christopher Ganotice
1 posts

Our Partners