productivity rates

Gentlemen,

Good day.

First of all,I would like to introduce to you myself briefly.My name is Leon Rosario currently working in Hydro-Projects.My previous exposure was purely electro-mechanical(external works).Moreso,in parralel to my working experience in view of scheduling for my new job(civil works).I am facing a problem in reinforcing bars production rate for structures.

I need your help maybe you can give me some links or further information regarding rebars installation productivity rates.

Thank you in advance.

 

Best wishes,

Leon Rosario

  

P
PRAPHULJITH KC 👤 Member for 13 years 3 months

Hello Everyone ,

Can any body tell me why some activities are show as critical when there is a positive total float for that activity. I believe critical activities have total float less than or equal to zero.

 

Thank You.

L
Leon Rosario 👤 Member for 13 years 3 months

Dear Mr.Bogdan,

I would like to take a quick moment to thank you for such great info.

Best Wishes,

Leon Rosario

B
Bogdan Leonte 👤 Member for 13 years 9 months

After a quick search I found the following:

 

Rebar Crew Productivity



 
Slabs 350 lb/ch pounds of steel per crew hour.

Footings 130 lbs/ch

Foundation 187 lbs/ch



Forming Crew Productivity



Slabs 36 sfca /ch

Footings 11.5 sfca/ch

Mat Footing 6.9 sfca/ch

Foundation 11.84 sfca/ch

Suspended Slab Underside 10.64 sf/ch

Suspended Slab Edge/Bulkhead 34.48 lf/ch




Hope these help.




Regards,

Bogdan

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts