Gentlemen,
Good day.
First of all,I would like to introduce to you myself briefly.My name is Leon Rosario currently working in Hydro-Projects.My previous exposure was purely electro-mechanical(external works).Moreso,in parralel to my working experience in view of scheduling for my new job(civil works).I am facing a problem in reinforcing bars production rate for structures.
I need your help maybe you can give me some links or further information regarding rebars installation productivity rates.
Thank you in advance.
Best wishes,
Leon Rosario
Hello Everyone ,
Can any body tell me why some activities are show as critical when there is a positive total float for that activity. I believe critical activities have total float less than or equal to zero.
Thank You.
Dear Mr.Bogdan,
I would like to take a quick moment to thank you for such great info.
Best Wishes,
Leon Rosario
After a quick search I found the following:
Footings 130 lbs/ch
Foundation 187 lbs/ch
Slabs 36 sfca /ch
Footings 11.5 sfca/ch
Mat Footing 6.9 sfca/ch
Foundation 11.84 sfca/ch
Suspended Slab Underside 10.64 sf/ch
Suspended Slab Edge/Bulkhead 34.48 lf/ch
Hope these help.
Regards,
Bogdan