When importing programme to P6 from MS project ,how to assign the baseline

Hi All,

I was importing programme from MS project to P6.It's quite difficult to assign a baseline on the progress programme,because everymonth there will be new activities added to MS project.So when import this to P6 and assigning the baseline to this takes a lot of time.

Is there a quick way to fix this.

Comments and help appreciated from everybody.

Thanks,
Rinet

R
Rinet Sebastian 👤 Member for 13 years 6 months

Hi Dieter,

Thanks for the reply.I am not quite clear about the user defined fields.If you don't mind can you explain me how to do the user defined fields for importing to P6 and assigning the baseline for MSP programme.

Thanks,

Rinet 

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Rinet

I'm afraid there is no other way, due to the different concepts of baselining.

MSP: Some fields added to the plan

P6: A complete copy of the the project.

I didn't check, but it should be possible to use the user defined fields to keep the information.

 

Good Luck!

Dieter

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts