Hi All,
I was importing programme from MS project to P6.It's quite difficult to assign a baseline on the progress programme,because everymonth there will be new activities added to MS project.So when import this to P6 and assigning the baseline to this takes a lot of time.
Is there a quick way to fix this.
Comments and help appreciated from everybody.
Thanks,
Rinet
Hi Dieter,
Thanks for the reply.I am not quite clear about the user defined fields.If you don't mind can you explain me how to do the user defined fields for importing to P6 and assigning the baseline for MSP programme.
Thanks,
Rinet
Hi Rinet
I'm afraid there is no other way, due to the different concepts of baselining.
MSP: Some fields added to the plan
P6: A complete copy of the the project.
I didn't check, but it should be possible to use the user defined fields to keep the information.
Good Luck!
Dieter