Microsoft Project 2010 Links

Does anyone know if there a way that I can just show all the tasks that are linked.  Rather than having to go through the tasks individually?

M
Mike Sallese 👤 Member for 17 years 6 months

@Mike Testro:

The first time I opened an MSP schedule, I noticed that you didn't have to link activities because MSP would follow the logic of Task 1 is succeeded by Task 2 and so on.  If you wanted any different relationships, you had to add them.

K
Khaja Sharief 👤 Member for 17 years 8 months

Insert predecessor and successor columns in the Gant Chart view. This lets you know that activities which have no links i.e. where predecessor and successor cell is blank. Just use filter option to filterout the activites which have no successor and predecessor.

R
Rafael Davila 👤 Member for 22 years 3 months

Do you mean filter for activities linked to selected?

 Photobucket

Better than leapfrogging.

Photobucket

I also find useful to filter for activities with links that are out-of-sequence and at the same time filter to display only those links.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Yvonne

Why have you got tasks with no links - every task must have at least 1 predecessor and 1 sucessor excpet the first and last tasks.

There is probably a filter that selects tasks with no links.

Best regards

Mike Testro

P
Paul Clarke 👤 Member for 18 years 10 months

I must admit I don't understand your question, can you explain further ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts