The first time I opened an MSP schedule, I noticed that you didn't have to link activities because MSP would follow the logic of Task 1 is succeeded by Task 2 and so on. If you wanted any different relationships, you had to add them.
Insert predecessor and successor columns in the Gant Chart view. This lets you know that activities which have no links i.e. where predecessor and successor cell is blank. Just use filter option to filterout the activites which have no successor and predecessor.
Member for
16 years 11 months@Mike Testro:The first time I
@Mike Testro:
The first time I opened an MSP schedule, I noticed that you didn't have to link activities because MSP would follow the logic of Task 1 is succeeded by Task 2 and so on. If you wanted any different relationships, you had to add them.
Member for
14 years 8 monthshi,Perhapse this toolbar will
hi,
Perhapse this toolbar will meet your needs - http://www.tools4schedulers.com
Member for
21 years 8 monthsDo you mean filter for
Do you mean filter for activities linked to selected?
Better than leapfrogging.
I also find useful to filter for activities with links that are out-of-sequence and at the same time filter to display only those links.
Member for
17 years 1 monthInsert predecessor and
Insert predecessor and successor columns in the Gant Chart view. This lets you know that activities which have no links i.e. where predecessor and successor cell is blank. Just use filter option to filterout the activites which have no successor and predecessor.
Member for
19 years 10 monthsHi Yvonne Why have you got
Hi Yvonne
Why have you got tasks with no links - every task must have at least 1 predecessor and 1 sucessor excpet the first and last tasks.
There is probably a filter that selects tasks with no links.
Best regards
Mike Testro
Member for
18 years 3 monthsI must admit I don't
I must admit I don't understand your question, can you explain further ?