@Mike Testro:

The first time I opened an MSP schedule, I noticed that you didn't have to link activities because MSP would follow the logic of Task 1 is succeeded by Task 2 and so on.  If you wanted any different relationships, you had to add them.

Member for

21 years 8 months

Do you mean filter for activities linked to selected?

 Photobucket

Better than leapfrogging.

Photobucket

I also find useful to filter for activities with links that are out-of-sequence and at the same time filter to display only those links.

Member for

17 years 1 month

Insert predecessor and successor columns in the Gant Chart view. This lets you know that activities which have no links i.e. where predecessor and successor cell is blank. Just use filter option to filterout the activites which have no successor and predecessor.

Member for

19 years 10 months

Hi Yvonne

Why have you got tasks with no links - every task must have at least 1 predecessor and 1 sucessor excpet the first and last tasks.

There is probably a filter that selects tasks with no links.

Best regards

Mike Testro

Member for

18 years 3 months

I must admit I don't understand your question, can you explain further ?