I have amended some activities on the restored baseline and the dates are all accurate. When I then assign the baseline back to the main plan a couple of the baseline dates change back/ close to the data date. This only happens to a couple of activities. Any ideas?
Also I have tried adding new activities to the restored Baseline plan but when it is assigned to the main plan the activity is not present? I have checked all filter etc but cannot see a reason why.
Any help on either of these would be great.
Regards
Nath
Perhaps you are not actually looking at the baseline schedule that you think you are. Try http://www.planningplanet.com/forums/primavera-version-pm5-pm6/528595/cant-get-p6-assign-baseline-dates for more on this. Good luck!