Baselined dates change when assigned back to the plan

I have amended some activities on the restored baseline and the dates are all accurate.  When I then assign the baseline back to the main plan a couple of the baseline dates change back/ close to the data date.  This only happens to a couple of activities. Any ideas?

Also I have tried adding new activities to the restored Baseline plan but when it is assigned to the main plan the activity is not present?  I have checked all filter etc but cannot see a reason why.

Any help on either of these would be great.

 

Regards

Nath

Featured Partner

Top Posters

edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts
Christopher Ganotice
1 posts
Ola Gbotoso
0 posts

Our Partners