For an LSTK contract, if an item is deleted from the Scope of work, after the Contractual completion date, is the Adjustment order retroactive??? Actual completion certificate has not yet been issued
Retroactive Adjustment order
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Mike,
This omission of work as you rightly pointed out, doen't have a time impact. The proposed Adjustment order is for the Cost impact only. Since it is a deletion, I personally feel that this is not retroactive.
Regards
Betsy
Hi Betsy
An ommission of work from the agreed scope will not normally reduce the time for completion.
However an adjustment can often be made if there is a claim for extension of time in place.
Best regards
Mike Testro