For an LSTK contract, if an item is deleted from the Scope of work, after the Contractual completion date, is the Adjustment order retroactive??? Actual completion certificate has not yet been issued
Retroactive Adjustment order
Forum Sponsor
Top Posters
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Hi Mike,
This omission of work as you rightly pointed out, doen't have a time impact. The proposed Adjustment order is for the Cost impact only. Since it is a deletion, I personally feel that this is not retroactive.
Regards
Betsy
Hi Betsy
An ommission of work from the agreed scope will not normally reduce the time for completion.
However an adjustment can often be made if there is a claim for extension of time in place.
Best regards
Mike Testro