I would like to know if it is possible to create a “Tracking Gantt chart” in P6 just like that in MS Project. If anyone has an idea, I will appreciate it if that person sends me clear instruction or point me to a manual or tutorial.
Tracking Gantt Chart in P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Mike,
yes, it is; definitely!
Alexandre
Hi Alexandre
Is that like creating a "Baseline" chart in Asta Powerproject?.
Best regards
Mike Testro
Rafael,
1. Display the "Classic WBS Layaout", then save it as "Tracking Gantt with WBS"
2. Open the View, Bars dialog and tick the "Primary Baseline" bar; move the bar below the "Critical Remaining Work" bar
3. Open the View, Columns dialog and select the appropriate columns: Actual Start, Actual Finish, Actual Duration, Remaining Duration, etc... Remove the columns you do not want
4. Save again the layout
Alexandre