Tracking Gantt Chart in P6

I would like to know if it is possible to create a “Tracking Gantt chart” in P6 just like that in MS Project.  If anyone has an idea, I will appreciate it if that person sends me clear instruction or point me to a manual or tutorial.

M
Mike Testro 👤 Member for 20 years 6 months

Hi Alexandre

Is that like creating a "Baseline" chart in Asta Powerproject?.

Best regards

Mike Testro

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Rafael,

1. Display the "Classic WBS Layaout", then save it as "Tracking Gantt with WBS"

2. Open the View, Bars dialog and tick the "Primary Baseline" bar; move the bar below the "Critical Remaining Work" bar

3. Open the View, Columns dialog and select the appropriate columns: Actual Start, Actual Finish, Actual Duration, Remaining Duration, etc... Remove the columns you do not want

4. Save again the layout

Alexandre

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts