Create a copy of your updated programme, and re-name it something like "Baseline -data date"
Then Open your original programme, go to Project > Maintain baselines > Add > Convert another project > select your new baseline
Once that is done, go to Project > Assign baselines > select your new baseline from the drop-down list under whichever baseline type you want to assign it to (Project, primary, secondary, or tertiary)
Member for
13 years 3 monthsthanks gary
thanks gary
Member for
16 years 7 monthsCreate a copy of your updated
Create a copy of your updated programme, and re-name it something like "Baseline -data date"
Then Open your original programme, go to Project > Maintain baselines > Add > Convert another project > select your new baseline
Once that is done, go to Project > Assign baselines > select your new baseline from the drop-down list under whichever baseline type you want to assign it to (Project, primary, secondary, or tertiary)