Earned Labor Units

H
Henry Chiu 👤 Member for 14 years 11 months

Hi Everyone,

 

Can anybody advise on how to disconnect the duration from the labor units. This is possible in P3 (in options) , how ever in P6 once you change the remaining duration the earned labor units automatically changed. I dont need to change the remaining units as this will affect the S curve. Only the duration is changed not the remaining labor remains the same.

 

Any idea please.

 

Thanks

 

H
Henry Chiu 👤 Member for 14 years 11 months

Hi David,

 

Thanks for your reply

I already tried this changes,only thing is I need also to update the % complete units in order to determine the current earned units.But then if you change the % complete unitis the duration also automatically changes. I am not sure if there is any equivalent option in P6 like in P3.

 

Thanks

D
David Craig 👤 Member for 16 years 8 months

Hi Henry,

Would changing the duration type solve this? If you were to change it to something like fixed duration and units, this would keep the units the same, you can change the duration yourself, and only the units/time would change.

Hope this helps.

Regards,

David Craig

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts